Enaon EDA, a subsidiary of Enaon, informs that construction works for the development of the natural gas distribution network in the city of Igoumenitsa will be carried out until the end of November 2026 on the following streets:
- Evangelistrias (from Kyprou to Ethnikis Antistaseos), on 19 November 2026.
- Ethnikis Antistaseos (Paraliaki) (from Evangelistrias to Michala), on 20 November 2026.
- Patriarchou Athenagora and Souliou, asphalt restoration works on 21 November 2026.
- Ethnikis Antistaseos (Paraliaki) (from Evangelistrias to Michala), on 23 November 2026.
- Ethnikis Antistaseos (from Michala to Dionysiou Skylosofou), on 24 November 2026.
- Ethnikis Antistaseos (from Dionysiou Skylosofou to Dagkli), on 25 November 2026.
- Ethnikis Antistaseos (from Dagkli to Tzavelainas), on 26 November 2026.
- Ethnikis Antistaseos (from Tzavelainas to Ioanninon), on 27 November 2026.
- 28is Oktovriou (from Ioanninon to Agiou Donatou), on 28 November 2026.
- 28is Oktovriou (from Agiou Donatou to Efyras), on 29 November 2026.
It should be noted that excavation works on Ethnikis Antistaseos will be completed within November in order to allow for asphalt paving before the winter season.
Due to the execution of the above works, temporary traffic arrangements and restrictions on vehicle circulation will be implemented in the affected areas.
The construction works form part of the project for the development of the natural gas distribution network in Igoumenitsa, which is co-financed by the Public Investment Programme (PIP) and the company’s own funds. This is an important energy infrastructure project with long-term benefits for the local community.
As part of the project, all residential and commercial consumers are offered a 100% discount on connection fees.
For further information, citizens may visit the official Enaon website at the following link: