Information on the Procedure for Access to the Distribution Network
Home › Procedure and Criteria for Biomethane Production Unit access to the Distribution Networks of Enaon EDA › Information on the Procedure for Access to the Distribution Network
Information on the Procedure for Access to the Distribution Network
This Chapter provides information on the procedure followed for access of the Biomethane Unit to the distribution network.
Submission of forms and communication with Enaon EDA regarding management of the connection steps shall take place via the following email address: biomethane@ena-on.gr.
Connecting steps

Producer
Submission of a Connection Request
The prospective Biomethane Producer wishing to connect the Biomethane Unit to the distribution network shall submit a relevant request to the Operator, in accordance with the Biomethane Unit Connection Request Form.
Procedure and deadlines: Following submission, the Operator shall assess the Connection Request on the basis of the technical criteria of Chapter 3 and shall send a Connection Offer or a reasoned rejection within thirty (30) days from the date of submission of the Request
Where the Connection Request is rejected due to the inability to absorb the Biomethane produced, as described in Chapter 3, the reverse-flow solution towards the Transmission Network shall be examined in accordance with the procedure set out in Chapter 2.2.
Where the Request is incomplete, the Operator shall notify the applicant of the need to complete and/or amend the Biomethane Unit Connection Request, setting a deadline of five (5) Working Days.
It is noted that, pursuant to ar.7 of Law 5215/2025, completion of the environmental permitting process is a prerequisite for submission of the Connection Request Form.

Operator
Submission of the Connection Proposal.
The Connection Proposal includes the Technical Description of the Connection Works (Connection Study), including the materials and components required, the proposed Biomethane Unit Connection Agreement, an indicative schedule for execution and completion of the Connection Works, the budget of the Connection Works including any cost allocation as described in Chapter 4, and the amount of the guarantee to be paid.
Procedure and deadlines: The Producer shall assess and accept or reject the Connection Proposal within twenty (20) Working Days from the date on which the Connection Proposal is submitted. If the deadline expires, the Proposal shall be deemed rejected.
Acceptance of the Connection Proposal is a prerequisite for the Producer to apply to the competent Licensing Authority for issuance of the Installation Permit, pursuant to Law no.5215/2025 and the provisions of the Regulation on the Installation and Operation of Biomethane Production Units (OGG B’4170/31.07.2025).

Operator & Producer
Conclusion of the Connection Agreement.
Upon acceptance of the Connection Proposal by the Producer, a Biomethane Unit Connection Agreement shall be entered into between the Operator and the Biomethane Producer.
It is noted that, in the event of: (a) amendment or re-issuance of the Installation Permit, or (b) amendment of the Operating Permit, or (c) transfer* of ownership of the installation, an amendment to the Connection Agreement shall be required.
In the above cases, the Producer shall submit to the Operator the Request Form for Amendment of the Unit Connection Agreement, and the procedure under Step 2 above shall commence.
*Pursuant to the provisions of the Distribution Network Management Code, in the event of transfer of ownership of the installation, the Rquest Form for Amendment of the Agreement shall be submitted within ten (10) days from the date of transfer.

Operator
Execution of the Connection Works
Issuance of the Unit’s Installation Permit, in accordance with Law no.5215/2025 and the Regulation on the Installation and Operation of Biomethane Production Units, is a prerequisite for commencement of the Connection Works.
Procedure and deadlines: The Producer shall notify the Operator of the issuance or rejection of the Unit’s Installation Permit within five (5) Working Days from the date on which the licensing decision is notified.
The terms and conditions governing execution of the Connection Works and the procedure for access to the Biomethane Unit are set out in the Connection Agreement.

Producer
Request Form for Trial Operation of the Unit.
Upon completion of the Connection Works connecting the Unit to the Distribution Network, the Producer shall submit to the Operator a request for Trial Operation of the Unit, in accordance with the Biomethane Unit Trial Operation Request Form.
Pursuant to ar.7 of the Regulation on the Installation and Operation of Biomethane Production Units (OGG B’4170/31.7.2025), the request shall be accompanied, at a minimum, by a declaration of responsibility signed by the holder of the installation permit and the engineer supervising the installation, confirming that all works have been executed in accordance with the installation permit, the Connection Proposal, the applicable regulations and provisions of the Natural Gas Distribution Network Management Code, the terms of the Connection Agreement, and the rules of art and science.
Procedure and deadlines: The Operator shall examine the Trial Operation Request and notify the Biomethane Producer accordingly within twenty (20) Working Days from the date of submission.
Where the request is accepted, the Operator shall notify the Biomethane Producer of the terms, procedures and limitations applicable to the Trial Operation of the Biomethane Unit.
The Operator shall activate the trial operation within thirty (30) Working Days from the date of submission of the Trial Operation Request.

Operator & Producer
Trial Operation of the Biomethane Unit.
Trial operation of the Biomethane Unit constitutes a critical final stage before the Biomethane Unit is placed into operation. The purpose of trial operation is to verify the technical integrity, safety and performance specifications of the Unit, as well as to inspect the metering systems, so that the biomethane injected complies with the quality specifications defined in the Code and the Connection Agreement.
The duration of trial operation shall not exceed six (6) months, with the possibility of an extension of up to an additional four (4) months, upon request by the interested party and with the Operator’s consent.
In order to ensure timely and proper completion of the trial operation within the above deadline, the Operator shall take the necessary measures, including on-site inspection and inspection of the relevant facilities, as provided for in the Connection Agreement.

Producer
Request for a Certificate of Completion of Trial Operation.
Following completion of the Biomethane Unit’s trial operation, the Producer shall submit to the Operator the Trial Operation Completion Request Form.
Following assessment of the results of the Trial Operation in accordance with the conditions established under Step 5, the Operator shall examine the request and, within twenty (20) days of submission of the relevant request by the Producer, issue the Certificate of Completion of Trial Operation. The Certificate shall also record completion of the Connection Works and installation of the BMU, enabling the Producer to commence the procedure for obtaining the Unit’s Operating Permit, in accordance with Law no.5215/2025 and the Regulation on the Installation and Operation of Biomethane Production Units.
In the event of rejection of the Completion Request, the Operator shall provide the Biomethane Producer with its substantiated objections, together with relevant directions for remedying the grounds for rejection. The Biomethane Producer may continue trial operation of the Unit, subject to the Operator’s consent and provided that the deadlines of Step 6 are not exceeded.

Producer
Request for Activation of the Biomethane Unit.
Activation of operation of the Biomethane Unit shall take place following submission by the Producer to the Operator of a Biomethane Unit’s Activation request.
Issuance of the Unit’s Operating Permit is a prerequisite for acceptance of the request and commencement of operation of the Unit and distribution of the biomethane produced into the network.
Procedure and deadlines: The Operator shall examine the request against the criteria referred to above and notify the Producer within ten (10) Working Days of acceptance of the request, indicating the proposed activation date.
Pursuant to Law no.5215/2025 and the Code, the Operator shall not receive biomethane that: (a) does not comply with the specifications of the Regulation on the Installation and Operation of Biomethane Units; (b) originates from a unit that does not hold a valid operating permit; (c) is not included in a declaration by a Distribution User who has reserved corresponding entry capacity; or (d) does not comply with the terms and specifications of the Code and the Connection Agreement.